October 2012
Following completion of the site roads and turbine bases, erection of the 9 nr 2MW Vestas wind turbines will commence on 29th October. Work on site continues with Vibro Menard providing CMC ground improvement to 5 remaining crane hardstandings which will be fully complete in the next 6 weeks.