We have been awarded a contract by The Jockey Club at Cheltenham Racecourse to provide a foul water by-pass sewer that separates flows from the Main Grandstand and other facilities on site and involves 450m of 300mm diameter pipework plus associated manholes.  Start date will be the end of November 2019 with construction period of 10 weeks. 