November 2019


We have been awarded a contract by The Jockey Club at Cheltenham Racecourse to provide a foul water by-pass sewer that separates flows from the Main Grandstand and other facilities on site and involves 450m of 300mm diameter pipework plus associated manholes.  Start date will be the end of November 2019 with construction period of 10 weeks. 

  • ISO 9001, 14001, 45001
  • Investors in People
  • Achilles UVDB (Utilities Vendor database) and ‘Verify’ audit
  • Achilles Building Confidence
  • Member of CECA Midlands Region The Civil Engineering Contractors Association
  • CHAS Contractors Health & Safety Scheme
  • Construction-line
  • SAFEcontractor
  • Member of the BDA British Drilling Association
  • Social Mobility Pledge
  • Women into Construction
  • Real Living Wage
  • Science Based Target Initiative